PERFORMA FOR MONTHLY PROGRESS REPORT
REGARDING DEVELOPMENT SCHEMES
Municipal Committee SHARAQPUR SHARIF
|
Sr. No. |
Name of Scheme |
Date Of Approval Of The Scheme (Date of DDC / TDC Meeting) |
Date Of Award Of Contract |
Date of Completion Of The Project |
Approved Cost |
Contract Cost |
Expend: upto June 2011 |
Allocation 2011-12 |
Funds Released 2011-12 |
Total Cumulative Expenditure Till The Current Month |
% Financial Progress Till The Current Month |
% Physical Progress Till The Current Month |
Remarks |
1 |
Const. of Water Supply Scheme Near Chwk Masjad
Anwar-e-Madina Along Jaranwala Road City Sharaqpur |
17-5-10 |
15-6-10 |
15-12-2010 |
3.500 |
3.472 |
2.968 |
0.504 |
0.504 |
2.968 |
85% |
90% |
Could not become functional due to awaited electric
connection |
2 |
Const.of Parking Shed for Machinery MC Sharaqpur |
12-04-10 |
29-12-10 |
30-03-2011 |
1.500 |
1.485 |
0.665 |
0.820 |
0.820 |
0.665 |
44% |
50% |
W-I-P |
3 |
Construction of Drain, Soling, Nallah & P.C.C Ghazi Pur |
03-12-11 |
04-11-11 |
08-10-11 |
1.500 |
1.500 |
1.125 |
0.375 |
0.375 |
1.468 |
98% |
100% |
Completed |
4 |
Construction of Drain, Soling, Nallah & P.C.C Chak No. 23 |
03-12-11 |
04-11-11 |
10-10-11 |
8.000 |
8.000 |
4.117 |
3.883 |
3.883 |
7.827 |
98% |
98% |
W-I-P |
5 |
Construction of Drain, Soling, Nallah & P.C.C Essan Lasiyan
Wala Kho |
03-12-11 |
04-11-11 |
10-10-11 |
3.977 |
3.977 |
2.167 |
1.810 |
1.810 |
3.632 |
92% |
100% |
Completed |
6 |
Construction of Drain, Soling, Nallah & P.C.C Thatha Nolan
Nano Dogar |
03-12-11 |
04-11-11 |
08-10-11 |
1.500 |
1.500 |
0.423 |
1.077 |
1.077 |
1.023 |
68% |
100% |
Completed |
7 |
Construction of Nallah shair e rabbani chowk to saddique
akbar chowk |
15-08-11 |
11-11-11 |
05-10-12 |
1.998 |
1.981 |
- |
1.998 |
1.998 |
0.501 |
0.250 |
75% |
W-I-P |
8 |
Construction of Nallah saddiqu e akbar chowk to filteration
plant |
15-08-11 |
11-11-11 |
04-10-12 |
1.220 |
1.214 |
- |
1.220 |
1.220 |
- |
0% |
5% |
W-I-P |
9 |
providing/laying water supply pipe line 3" dia different
streets sharaqpur |
15-08-11 |
11-11-11 |
04-10-12 |
0.962 |
0.958 |
- |
0.962 |
0.962 |
0.738 |
77% |
100% |
Completed |
10 |
Construction of foot path both sides shair e rabbani chowk
to old jaranwala road |
15-08-11 |
11-11-11 |
03-10-12 |
0.932 |
0.926 |
- |
0.932 |
0.932 |
- |
0% |
30% |
W-I-P |
11 |
providing/laying water supply pipe line 6" dia from ground
to bara adda |
15-08-11 |
11-11-11 |
03-10-12 |
0.866 |
0.862 |
- |
0.866 |
0.866 |
0.308 |
35% |
55% |
W-I-P |
12 |
Construction of Nallah circular road city sharaqpur(balance
work) |
15-08-11 |
11-11-11 |
03-10-12 |
0.775 |
0.773 |
- |
0.775 |
0.775 |
- |
0% |
90% |
W-I-P |
13 |
Construction of hall and first floor main road near bara
adda |
15-08-11 |
11-11-11 |
03-10-12 |
0.765 |
0.758 |
- |
0.765 |
0.765 |
0.550 |
72% |
85% |
W-I-P |
14 |
Construction of slaughter house (balance work) |
15-08-11 |
11-11-11 |
03-10-12 |
0.740 |
0.736 |
- |
0.740 |
0.740 |
0.494 |
67% |
90% |
W-I-P |
15 |
Construction of R C C slabs with manhole covers 22"& 24" dia
from chotta adda to bara adda |
15-08-11 |
11-11-11 |
03-10-12 |
0.631 |
0.628 |
- |
0.631 |
0.631 |
0.560 |
89% |
90% |
W-I-P |
16 |
providing/fixing jully sliding bench etc childern park ,lady
park &T M A ground |
15-08-11 |
11-11-11 |
03-10-12 |
0.500 |
0.499 |
- |
0.500 |
0.500 |
- |
0% |
40% |
W-I-P |
17 |
Repiar / supply of manhole covers city sharaqpur |
15-08-11 |
11-11-11 |
02-10-12 |
0.400 |
0.399 |
- |
0.400 |
0.400 |
- |
0% |
25% |
W-I-P |
18 |
Construction of cattle shed(balance work) |
15-08-11 |
11-11-11 |
02-10-12 |
0.300 |
0.298 |
- |
0.300 |
0.300 |
0.247 |
82% |
85% |
W-I-P |
19 |
Construction of P.C.C Ayya Pur |
15-08-11 |
11-11-11 |
02-10-12 |
0.250 |
0.249 |
- |
0.250 |
0.250 |
0.249 |
100% |
100% |
Completed |
20 |
Repiar / construction of soling etc ramzan bazar |
15-08-11 |
11-11-11 |
01-10-12 |
0.170 |
0.169 |
- |
0.170 |
0.170 |
- |
0% |
0% |
Site Dispute |
21 |
Construction of P.C.C & drain tenday |
15-08-11 |
11-11-11 |
01-10-12 |
0.150 |
0.149 |
- |
0.150 |
0.150 |
0.126 |
85% |
100% |
Completed |
2nd Tender |
22 |
Const. of Drain & Streets etc Ghazi pur. |
14-03-2012 |
23-04-12 |
22-07-12 |
1.000 |
1.000 |
|
1.000 |
1.000 |
|
|
|
W-I-P |
23 |
Const. of Nallaha, Boundary wall & Gate Janaz Ghah etc
Niringni. |
14-03-2012 |
23-04-12 |
22-07-12 |
0.500 |
0.498 |
|
0.498 |
0.498 |
|
|
|
Nishan Given |
24 |
Const. of Drain & Streets etc Thatha Bolian Old Bheany. |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.500 |
|
0.500 |
0.500 |
|
|
|
Work order issued 23-04-2012 |
25 |
Const. of Drain & Streets etc Bhoaywal. |
14-03-2012 |
23-04-12 |
22-06-12 |
1.000 |
0.500 |
|
0.500 |
0.500 |
|
|
|
Work order issued 23-04-2012 |
26 |
Const. of Drain & Streets etc Triddaywali. |
14-03-2012 |
23-04-12 |
22-07-12 |
3.977 |
0.997 |
|
0.997 |
0.997 |
|
|
|
Work order issued 23-04-2012 |
27 |
Const. of Drain & Streets etc Rajian Araian. |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.498 |
|
0.498 |
0.498 |
|
|
|
Work order issued 23-04-2012 |
28 |
Const. of Drain & Streets etc Qila Ghouss. |
14-03-2012 |
23-04-12 |
22-07-12 |
0.700 |
0.699 |
|
0.699 |
0.699 |
|
|
|
Work order issued 23-04-2012 |
29 |
Const. of Drain & Streets etc Mahtam. |
14-03-2012 |
23-04-12 |
22-07-12 |
0.800 |
0.800 |
|
0.800 |
0.800 |
|
|
|
Work order issued 23-04-2012 |
30 |
Const. of Drain & Streets etc Hichki Pur Araian. |
14-03-2012 |
23-04-12 |
22-07-12 |
1.000 |
0.997 |
|
0.997 |
0.997 |
|
|
|
Nishan Given |
31 |
Const. of Drain & Streets etc Mir pur |
14-03-2012 |
23-04-12 |
22-07-12 |
1.000 |
0.990 |
|
0.990 |
0.990 |
|
|
|
Work order issued 23-04-2012 |
32 |
Const. of Drain & Streets etc Chack No.22 Rajpootan wala |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.499 |
|
0.499 |
0.499 |
|
|
|
Nishan Given |
33 |
Const. of Drain & Streets etc Dhaamkey |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.499 |
|
0.499 |
0.499 |
|
|
|
Work order issued 23-04-2012 |
34 |
Const. of Drain & Streets etc Nazar labana |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.500 |
|
0.500 |
0.500 |
|
|
|
Work order issued 23-04-2012 |
35 |
Const. of Drain & Streets etc Marh Bhangawan |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.499 |
|
0.499 |
0.499 |
|
|
|
Nishan Given |
36 |
Const. of Drain & Streets etc Fattu Wala |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.499 |
|
0.499 |
0.499 |
|
|
|
Nishan Given |
37 |
Const. of Drain & Streets etc Baig Pur |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.499 |
|
0.499 |
0.499 |
|
|
|
Work order issued 23-04-2012 |
38 |
Const. of Drain & Streets etc Hassan Kot |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.496 |
|
0.496 |
0.496 |
|
|
|
Work order issued 23-04-2012 |
39 |
Const. of Drain & Streets etc Jhugiyan |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.498 |
|
0.498 |
0.498 |
|
|
|
Work order issued 23-04-2012 |
40 |
Const. of Drain & Streets etc Jhandy wala |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.499 |
|
0.499 |
0.499 |
|
|
|
Work order issued 23-04-2012 |
41 |
Const. of Drain & Streets etc Thatha ladwy |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.499 |
|
0.499 |
0.499 |
|
|
|
Nishan Given |
42 |
Const. of Drain & Streets etc Thatha Bhuttian |
14-03-2012 |
23-04-12 |
22-06-12 |
0.150 |
0.150 |
|
0.150 |
0.150 |
|
|
|
Work order issued 23-04-2012 |
43 |
Const. of Drain & Streets etc Mehta Tridda |
14-03-2012 |
23-04-12 |
22-06-12 |
0.500 |
0.498 |
|
0.498 |
0.498 |
|
|
|
Work order issued 23-04-2012 |
44 |
Const. of Drain & Streets etc Thatha Nol Nano Dogar |
14-03-2012 |
23-04-12 |
22-07-12 |
1.000 |
0.998 |
|
0.998 |
0.998 |
|
|
|
Work order issued 23-04-2012 |
45 |
Const. of Drain & Streets etc Thatha Bamian |
14-03-2012 |
23-04-12 |
22-07-12 |
1.000 |
1.000 |
|
1.000 |
1.000 |
|
|
|
W-I-P |
46 |
Const. of Drain & Streets etc Noor Pur Araian |
14-03-2012 |
23-04-12 |
22-07-12 |
0.700 |
0.699 |
|
0.699 |
0.699 |
|
|
|
Nishan Given |
47 |
Const. of Drain & Streets etc Chah kokran wala |
14-03-2012 |
23-04-12 |
22-05-12 |
0.100 |
0.998 |
|
0.998 |
0.998 |
|
|
|
Nishan Given |
48 |
Const. of Drain & Streets etc Chah Loharan |
14-03-2012 |
23-04-12 |
22-05-12 |
0.200 |
0.200 |
|
0.200 |
0.200 |
|
|
|
Nishan Given |
49 |
Const. of Drain & Streets etc Ayya pur |
14-03-2012 |
23-04-12 |
22-07-12 |
1.000 |
0.998 |
|
0.998 |
0.998 |
|
|
|
Nishan Given |
50 |
Const. of Drain & Streets etc Thatha Kanyan |
14-03-2012 |
23-04-12 |
22-06-12 |
0.400 |
0.399 |
|
0.399 |
0.399 |
|
|
|
Nishan Given |
3rd Tender |
51 |
Const. of Drain & Streets etc Bholay Shah |
24-03-12 |
23-04-12 |
22-07-12 |
1.000 |
0.990 |
|
0.990 |
0.990 |
|
|
|
Nishan Given |
52 |
Const. of, Boundary wall etc Grave yard Mir pur . |
24-03-12 |
23-04-12 |
22-07-12 |
1.000 |
0.999 |
|
0.999 |
0.999 |
|
|
|
W-I-P |
53 |
Const. of Drain & Streets etc Naseer Abad. |
24-03-12 |
23-04-12 |
22-07-12 |
1.000 |
0.992 |
|
0.992 |
0.992 |
|
|
|
Work order issued 23-04-2012 |
54 |
Const. of Drain & Streets etc Ghazi pur.. |
24-03-12 |
23-04-12 |
22-07-12 |
1.000 |
0.999 |
|
0.999 |
0.999 |
|
|
|
Nishan Given |
55 |
Const. of Drain & Streets etc Qila Ghouss. |
24-03-12 |
23-04-12 |
22-07-12 |
1.000 |
0.999 |
|
0.999 |
0.999 |
|
|
|
Work order issued 23-04-2012 |
56 |
Const. of Drain & Streets etc Thatha Bamian. |
24-03-12 |
23-04-12 |
22-07-12 |
1.000 |
0.997 |
|
0.997 |
0.997 |
|
|
|
W-I-P |
57 |
Const. of Drain & Streets etc.Chak No.13 |
24-03-12 |
23-04-12 |
22-07-12 |
1.000 |
0.991 |
|
0.991 |
0.991 |
|
|
|
Work order issued 23-04-2012 |
58 |
Const. of Drain & Streets etc Maddar Sharif. |
24-03-12 |
23-04-12 |
22-07-12 |
1.000 |
0.992 |
|
0.992 |
0.992 |
|
|
|
Nishan Given |
59 |
Const. of Drain & Streets etc Thatha lahway. |
24-03-12 |
23-04-12 |
22-07-12 |
1.000 |
0.999 |
|
0.999 |
0.999 |
|
|
|
Nishan Given |
60 |
Const. of Drain & Streets etc Kukri Pur |
24-03-12 |
23-04-12 |
22-07-12 |
0.900 |
1.000 |
|
1.000 |
1.000 |
|
|
|
Work order issued 23-04-2012 |
61 |
Providing Laying (PVC) Water Supply Line Main Jaranwala Road
Sharaqpur |
24-03-12 |
23-04-12 |
22-06-12 |
0.850 |
0.899 |
|
0.899 |
0.899 |
|
|
|
Nishan Given |
62 |
Providing Laying (PVC) Water Supply Line Different streets
Sharaqpur |
24-03-12 |
23-04-12 |
22-06-12 |
0.700 |
0.849 |
|
0.849 |
0.849 |
|
|
|
W-I-P |
63 |
Const. of Nallha (Balance work) Share-e-Rabbani Chowk to
Sadiq-e-Akbar Chowk Sharaqpur |
14-03-2012 |
23-04-12 |
22-06-12 |
0.700 |
0.699 |
|
0.699 |
0.699 |
|
|
|
W-I-P |
64 |
Const. of Drain & Streets etc Bighen Pura |
24-03-12 |
23-04-12 |
22-06-12 |
0.700 |
0.693 |
|
0.693 |
0.693 |
|
|
|
Work order issued 23-04-2012 |
65 |
Const. of Drain & Streets etc Southern Abadi Ayya Pur |
24-03-12 |
23-04-12 |
22-06-12 |
0.700 |
0.699 |
|
0.699 |
0.699 |
|
|
|
Work order issued 23-04-2012 |
66 |
Const. of Drain & Streets etc Jalal Pur |
24-03-12 |
23-04-12 |
22-06-12 |
0.700 |
0.699 |
|
0.699 |
0.699 |
|
|
|
Work order issued 23-04-2012 |
67 |
Const. of Drain & Streets etc Dhana Khukhran |
24-03-12 |
23-04-12 |
22-06-12 |
0.700 |
0.694 |
|
0.694 |
0.694 |
|
|
|
Work order issued 23-04-2012 |
68 |
Const. of Drain & Streets etc Khana Wali |
24-03-12 |
23-04-12 |
22-06-12 |
0.500 |
0.496 |
|
0.496 |
0.496 |
|
|
|
Work order issued 23-04-2012 |
69 |
Const. of Drain & Streets etc Darbar Baba Bholay Shah Bhoy
Dhaku |
24-03-12 |
23-04-12 |
22-06-12 |
0.500 |
0.499 |
|
0.499 |
0.499 |
|
|
|
Nishan Given |
70 |
Const. of Drain & Streets etc Jhanda |
24-03-12 |
23-04-12 |
22-06-12 |
0.500 |
0.496 |
|
0.496 |
0.496 |
|
|
|
Work order issued 23-04-2012 |
71 |
Const. of Drain & Streets etc Ladhay |
24-03-12 |
23-04-12 |
22-06-12 |
0.500 |
0.497 |
|
0.497 |
0.497 |
|
|
|
Nishan Given |
72 |
Const. of Drain & Streets etc Bhoy Dhaku |
24-03-12 |
23-04-12 |
22-06-12 |
0.500 |
0.499 |
|
0.499 |
0.499 |
|
|
|
Work order issued 23-04-2012 |
73 |
Const. of Drain & Streets etc Dholay Da Wara |
24-03-12 |
23-04-12 |
22-06-12 |
0.400 |
0.398 |
|
0.398 |
0.398 |
|
|
|
W-I-P |
74 |
Const. of Bridge etc Chah kukran wala |
24-03-12 |
23-04-12 |
22-06-12 |
0.300 |
0.300 |
|
0.300 |
0.300 |
|
|
|
W-I-P |